Preparing elevator specifications for a project requires more than selecting a rated load, speed, and cab size. A complete specification translates the building’s operational needs into measurable equipment requirements, coordinated construction interfaces, defined supplier responsibilities, and verifiable acceptance criteria.
For architects, developers, contractors, and procurement teams, the objective is to produce an elevator specification that suppliers can price consistently and that the project team can review, approve, and implement without relying on unresolved assumptions.
This guide explains how to prepare elevator technical specifications, coordinate building interfaces, compare supplier proposals, and develop an elevator specification template for project use.
Define the Project Requirements Before Selecting Equipment
Start by identifying how the building will use its elevators. The building’s purpose, expected traffic, floor layout, accessibility requirements, and goods-handling needs determine which equipment configurations are appropriate.
Identify the Elevator Type and Intended Use
Different applications create different specification priorities.
- Commercial passenger elevators must accommodate passenger traffic, waiting-time expectations, accessibility, and the building’s operating schedule. See EKCNE’s commercial elevator systems.
- Residential elevators prioritize appropriate capacity, convenient access, ride comfort, and integration with residential layouts.
- Medical passenger elevators may need to accommodate beds, stretchers, medical equipment, and accompanying personnel. Their required dimensions and operating functions should be established from the actual clinical workflow.
- Industrial and freight elevators require careful evaluation of cargo dimensions, loading methods, concentrated loads, and the dimensions and weight of handling equipment. Review industrial lift systems where relevant.
- Accessibility lifts may be suitable for particular building layouts or access requirements, subject to the applicable regulations and intended use.
Record the intended use of every elevator separately. A project with passenger, service, and freight elevators should not rely on one generic specification for all equipment.
Collect the Building and Traffic Information
Before determining the number of elevators or their rated performance, document the following inputs:
- Building type, occupancy, and expected population.
- Number of floors, floor-to-floor heights, and total travel.
- Number and location of entrances and elevator stops.
- Peak traffic periods and expected passenger movement between floors.
- Goods movement, delivery schedules, and loading requirements.
- Accessibility needs and any dedicated emergency or service functions.
- Expected operating hours and future changes in building use.
For passenger elevators, traffic analysis can help compare candidate configurations. Depending on the project, the analysis may assess handling capacity, waiting time, journey time, and the effect of different elevator quantities, rated loads, speeds, and control strategies.
The output should support a design decision rather than automatically prescribe a single configuration. The selected solution must also satisfy building constraints, applicable regulations, operating requirements, and budget limitations.
For freight elevators, passenger traffic analysis alone is insufficient. The team must evaluate cargo dimensions, load distribution, handling equipment, loading frequency, and the time required for loading and unloading.
Select the Elevator System Based on Project Constraints
The specification should explain the required performance and building interfaces without unnecessarily restricting the supplier to one technical arrangement.
Compare Traction, Hydraulic, and Machine-Room-Less Systems
The appropriate system depends on travel distance, rated load, equipment location, maintenance access, energy requirements, and local conditions.
| Evaluation factor | Traction elevator | Hydraulic elevator | Machine-room-less (MRL) elevator |
|---|---|---|---|
| Drive arrangement | Uses a traction machine and suspension system | Uses hydraulic power to move the car | Uses traction technology with equipment arranged to reduce the need for a separate machine room |
| Building space | Depends on the machine-room arrangement | Requires space for the hydraulic equipment and associated installation | Reduces the need for a separate machine room but still requires equipment and service clearances |
| Travel and performance | Can support a wide range of travel and speed requirements, depending on the design | Often considered for shorter-travel applications, subject to the project requirements | Depends on the selected traction system and its rated performance |
| Maintenance considerations | Requires safe access to the machine, controls, and other service points | Requires access to hydraulic equipment and associated components | Requires planned access to the machine, controller, and other equipment within or adjacent to the hoistway |
| Main design considerations | Machine arrangement, suspension, structural loads, and maintenance access | Equipment location, hydraulic system requirements, heat management, and maintenance access | Hoistway arrangement, controller location, access provisions, and equipment replacement strategy |
These are general characteristics, not universal selection rules. Final suitability must be assessed against the proposed equipment, building layout, applicable regulations, and the owner’s maintenance strategy.
An MRL arrangement, for example, may reduce dedicated machine-room requirements, but it does not eliminate the need for safe inspection access, controller access, or a practical equipment replacement route.
When requesting proposals, specify the required outcomes and constraints. Allow technically compliant alternatives where the project permits them, provided suppliers document their differences and demonstrate compliance.

Establish the Core Elevator Technical Specifications
Once the project requirements and candidate system have been established, convert them into a structured schedule for each elevator.
Rated Load and Car Dimensions
Rated load must reflect the intended use of the elevator, but capacity alone does not establish whether the car is suitable.
For passenger elevators, consider expected occupancy, accessibility, and the dimensions required by the intended use. For freight elevators, verify that the car can accommodate the actual cargo and loading method.
The specification should record:
- Rated load in kilograms or pounds.
- Required internal car width and depth.
- Clear entrance width and height.
- Cargo dimensions and loading arrangement, where applicable.
- Concentrated or distributed loads relevant to the application.
- Dimensions and weight of trolleys, pallet trucks, or other handling equipment.
- Any special requirements for beds, stretchers, wheelchairs, or oversized items.
For example, a freight elevator may have sufficient rated load for a pallet but still be unsuitable if the pallet cannot pass through the entrance or turn within the available space. The loading arrangement must therefore be checked alongside capacity.
Rated Speed and Control Strategy
Rated speed should be selected in conjunction with travel distance, traffic demand, number of stops, and expected service performance.
The specification should identify the required rated speed, the number of elevators, the stops served, and any necessary control functions. For multiple elevators, determine whether independent, parallel, or group control is appropriate to the traffic and operating requirements.
Do not specify speed solely from the number of floors. Compare candidate configurations against the results of the project’s traffic analysis and the physical limitations of the proposed equipment.
Performance and Operating Requirements
Performance requirements should be measurable or otherwise objectively verifiable.
Depending on the project, the schedule may address:
- Ride comfort and vibration.
- Leveling performance at landings.
- Door operation and obstruction protection.
- Noise limits in relevant occupied areas.
- Energy performance, where a defined assessment method is required.
- Accessibility functions and user interfaces.
- Emergency communication and applicable emergency operating functions.
- Control-system interfaces with building services.
Avoid wording such as “excellent ride quality” or “low noise” without a defined criterion. If the project team has not established a numerical limit, identify the requirement as an open item rather than inventing a value.
For each key requirement, record the acceptance criterion, verification method, test conditions, required evidence, and responsible party. This makes it possible to assess supplier compliance and verify performance during commissioning.
Coordinate Building Interfaces and Civil Requirements
Building interfaces must be coordinated before equipment dimensions and construction details are finalized. The specification should identify the required dimensions, their source, and whether they have been confirmed.
Record the Critical Hoistway and Building Dimensions
The elevator schedule should include the following fields for each unit.
| Specification field | Information to record |
|---|---|
| Hoistway clear width and depth | Required internal shaft dimensions and the relevant drawing reference |
| Pit depth | Available and required pit depth, subject to equipment-specific confirmation |
| Overhead clearance | Available space above the top landing and the approved equipment requirement |
| Floor-to-floor heights | Vertical distances between consecutive served floors |
| Total travel | Vertical distance between the lowest and highest served landings |
| Number of stops | Total stops and identification of each landing |
| Entrance arrangement | Entrance side, door configuration, and clear opening dimensions |
| Car internal dimensions | Required car width, depth, and height where applicable |
| Machine-room arrangement | Dedicated room, MRL equipment arrangement, or other approved configuration |
| Structural loads | Supplier-provided loads and the corresponding structural review |
| Installation clearances | Required working, inspection, and maintenance clearances |
| Dimension status | Preliminary, drawing-based, site-measured, or approved |
| Drawing revision | Drawing number, revision, and date used for coordination |
The distinction between preliminary, drawing-based, site-measured, and approved dimensions is important. A preliminary architectural dimension should not be treated as a final manufacturing instruction.
Each dimensional requirement should be traceable to a drawing or an approved technical submission. When the site condition differs from the design documents, record the discrepancy and assign responsibility for resolving it before the affected work proceeds.

Coordinate Structural, Electrical, and Environmental Requirements
Elevator installation involves more than the hoistway itself. The project team should coordinate:
- Structural support and loads associated with the selected equipment.
- Required openings, embedded items, and mounting provisions.
- Main electrical supply and equipment disconnect requirements.
- Car lighting and other required electrical services.
- Controller and machine access.
- Ventilation or temperature-control requirements where applicable.
- Pit drainage and protection against water ingress.
- Construction access, equipment delivery routes, and replacement access.
- Interfaces with fire protection, emergency power, and building control systems where required.
The elevator supplier should provide the technical information needed for the relevant design disciplines to review these interfaces. The architect, structural engineer, electrical engineer, general contractor, and other responsible parties should confirm their respective obligations.
Do not use generic shaft dimensions as final construction requirements. Actual pit depth, overhead clearance, car dimensions, and structural loads must be coordinated with the proposed equipment and the applicable regulations.
Define Applicable Safety, Regulatory, and Accessibility Requirements
The specification should identify the regulations and technical requirements applicable to the project’s location, elevator type, intended use, and approval process.
Do not assume that a standard used in one country or region automatically applies in another. Confirm the applicable editions, amendments, local requirements, and authority having jurisdiction before finalizing the specification.
Translate Safety Requirements Into Verifiable Obligations
A general statement that the elevator must comply with applicable safety requirements is not sufficient on its own. Each relevant requirement should be translated into a defined function and a method of verification.
| Field | What to specify |
|---|---|
| Applicable requirement | Relevant regulation, technical code, or contractual requirement |
| Required function | The safety or operating function the equipment must provide |
| Technical evidence | Required drawings, technical documents, certificates, or other evidence |
| Verification stage | Design review, installation inspection, functional test, or statutory inspection |
| Acceptance responsibility | Party responsible for performing, reviewing, and approving the evidence |
Depending on the elevator type and project requirements, the schedule may need to address door interlocks, door protection, overspeed protection, emergency communication, overload protection, emergency operation, and other applicable safety functions.
The exact requirements must be established from the applicable rules and equipment design. Do not transfer numerical values from an older technical reference without verifying their current applicability.
Specify Accessibility and Special Operating Functions
Accessibility requirements may affect car dimensions, entrance width, controls, handrails, signals, and the surrounding lobby. Compliance must be considered as part of the building layout, not solely as an equipment selection issue.
For hospitals, high-rise buildings, and other projects with special operating requirements, identify any required emergency functions and their interfaces with the building’s electrical, fire protection, access control, and communication systems.
For each special function, state whether it is mandatory, preferred, or optional, and identify how compliance will be demonstrated.
Build an Elevator Specification Template
An elevator specification template should be a working project document rather than a simple list of technical parameters. It must connect each requirement to its source, supplier response, verification method, and approval status.
Project Information and Document Register
Begin with the project-level information needed to prepare a consistent request for quotation (RFQ).
| Field | Required information |
|---|---|
| Project name and location | Project identification and target jurisdiction |
| Design stage | Concept design, budget quotation, tender, or construction |
| Document register | Document title, number, revision, and date |
| Elevator ID | Unique identifier for each elevator |
| Quotation due date | Required date for supplier responses |
| Required delivery date | Target delivery date or site requirement |
| Quotation basis | Currency, delivery terms, and scope assumptions |
| Open items | Unresolved questions, assigned owner, and due date |
A target delivery date should not be treated as a confirmed supplier commitment. The quotation should clarify the proposed lead time, its starting point, and any conditions that could affect it.
Per-Elevator Specification Schedule
Use one record for each elevator, or for each genuinely identical group of units.
| Field | Purpose |
|---|---|
| Elevator ID and type | Identifies the equipment and intended use |
| Rated load and speed | Records the required primary parameters |
| Stops and total travel | Defines the service range |
| Car and entrance dimensions | Establishes the required usable space |
| Drive and equipment arrangement | Records the required or proposed system |
| Control and special functions | Identifies operating and interface requirements |
| Building interface data | Records hoistway, pit, overhead, structural, and electrical requirements |
| Requirement type | Mandatory, preferred, or optional |
| Source and drawing revision | Identifies the origin and version of the requirement |
| Supplier response | Compliant, proposed alternative, deviation, excluded, or pending |
| Verification method | Defines how the requirement will be checked |
| Responsible party | Assigns responsibility for review or resolution |
| Status and due date | Tracks approval and outstanding actions |
| Test or submittal reference | Links the requirement to supporting evidence |
| Approval status | Records whether the evidence has been accepted |
For multiple units, keep separate records whenever the served floors, dimensions, operating functions, or building interfaces differ. Shared requirements can be referenced, but the project team must still be able to trace each elevator’s compliance independently.
Evaluate Elevator Tender Specifications and Supplier Quotations
Once suppliers receive the specification, the procurement team should evaluate technical compliance and commercial scope separately. A lower quotation is not necessarily comparable if it excludes required functions, uses different assumptions, or leaves building interfaces unresolved.
Review Technical Compliance and Deviations
Require each supplier to identify its response to every mandatory requirement. Avoid accepting a general statement that the proposed equipment complies with the specification without supporting details.
Classify responses into four categories:
- Compliant: The proposed solution meets the stated requirement.
- Alternative proposed: The supplier proposes a different solution and provides the technical basis for review.
- Non-compliant: The proposal does not meet a mandatory requirement.
- Pending or excluded: The information is missing, unresolved, or outside the quoted scope.
Each deviation should identify the affected requirement, the proposed alternative, the technical and building impacts, and the party responsible for approval.
Deviations affecting safety, statutory compliance, accessibility, structural interfaces, or critical dimensions must be resolved through the appropriate review and approval process before the affected work proceeds. Any mandatory non-compliance must be addressed before award or handled through a formally permitted process under the project’s rules.
Compare the Commercial Scope
The quotation review should also confirm:
- Included equipment, accessories, and special functions.
- Installation, testing, commissioning, and inspection support.
- Freight, packaging, delivery terms, and unloading responsibilities.
- Required civil works and electrical provisions.
- Exclusions, provisional items, and assumptions.
- Quotation validity and payment terms.
- Proposed manufacturing and delivery lead times.
- Warranty conditions, maintenance documentation, and spare-parts information.
A responsibility matrix can help distinguish the supplier’s obligations from those of the owner, architect, contractor, and other trades. For example, the elevator supplier may provide equipment loads and layout drawings, while the project’s structural engineer remains responsible for reviewing the building structure.
Use the same specification revision and commercial assumptions when comparing proposals. Otherwise, apparent price differences may reflect different scopes rather than genuine cost advantages.
Manage Technical Submittals, Approvals, and Installation Readiness
A specification becomes effective only when its requirements are carried through design coordination, equipment manufacturing, installation, and acceptance.
Establish the Technical Submittal Schedule
Depending on the project scope, required submissions may include:
- Elevator schedule and technical compliance statement.
- General arrangement drawings and hoistway layouts.
- Pit, overhead, and entrance details.
- Structural load information.
- Electrical supply and interface requirements.
- Control and special-function descriptions.
- Performance and testing documentation.
- Installation and delivery schedule.
- Operation, maintenance, warranty, and spare-parts documentation.
Record each submission’s document number, revision, submission date, review status, reviewer, and approval date. A revised drawing should be checked against the previous approved version so that changes affecting other trades are not overlooked.
Define Construction Hold Points
Before equipment manufacture or installation reaches a point where changes become difficult or costly, identify the required approvals.
Typical review points include:
- Confirmation of the project requirements and applicable regulations.
- Review of the supplier’s technical proposal and deviations.
- Coordination of the general arrangement drawings with architectural and structural documents.
- Confirmation of electrical, safety, and other building interfaces.
- Verification that the relevant site dimensions and construction conditions are ready.
- Approval of required testing, commissioning, and handover documentation.
The exact sequence depends on the project contract and construction program. An approval should not be treated as complete merely because a document has been submitted. The review outcome and any outstanding conditions must be recorded.
Verify Performance and Complete Handover
The handover process should distinguish statutory inspection, contractually required performance testing, commissioning records, and final documentation.
Match Each Requirement to Its Acceptance Evidence
For every important performance or safety requirement, the project team should be able to answer five questions:
- What must the equipment achieve?
- What constitutes an acceptable result?
- How and under what conditions will it be verified?
- Which record or document proves the result?
- Who is responsible for reviewing and accepting the evidence?
Depending on the contract and applicable rules, evidence may include approved drawings, test records, inspection documents, certificates, and commissioning reports.
Do not assume that passing a statutory inspection automatically confirms every contractual performance requirement. Conversely, a successful functional test does not replace any legally required inspection or approval.
Complete the Handover Package
Before final acceptance, confirm the required handover items, including:
- Applicable inspection and approval documentation.
- Commissioning and functional test records.
- Final approved drawings and equipment schedules.
- Operating and maintenance instructions.
- Warranty information and service contacts.
- Recommended spare parts and relevant technical information.
- Emergency procedures and operating instructions.
- Outstanding defects, corrective actions, and agreed closure dates.
The owner or designated representative should confirm that the required documents have been received and that unresolved items have been assigned for action.
Elevator Specification Checklist
Use this checklist before issuing an RFQ or approving a supplier’s technical proposal.
- The project location, design stage, and applicable regulations are confirmed.
- Each elevator has a unique identifier and a clearly defined intended use.
- Rated load, speed, stops, travel, car dimensions, and entrance dimensions are recorded.
- Passenger traffic or freight-handling requirements have been assessed.
- Hoistway dimensions, pit depth, overhead clearance, and structural loads have documented sources and status.
- Electrical, environmental, maintenance, and building-system interfaces are identified.
- Safety, accessibility, and special operating requirements are linked to applicable criteria.
- Each mandatory requirement has a defined verification method.
- Supplier compliance, alternatives, deviations, exclusions, and pending items are documented.
- Quotation scope, delivery assumptions, lead time, warranty, and service documentation are compared consistently.
- Technical submittal revisions and approval responsibilities are recorded.
- Testing, statutory inspection, commissioning, and handover requirements are defined.
If any critical item remains unresolved, record the issue, responsible party, due date, and the approval required before the relevant project milestone.
Conclusion
Preparing elevator specifications for a project requires coordinated decisions about equipment performance, building dimensions, safety requirements, supplier scope, and acceptance evidence. A structured specification makes these decisions traceable and gives the project team a consistent basis for reviewing technical proposals and managing installation interfaces.
For project teams evaluating elevator systems or components, EKCNE provides information on elevator systems and elevator components. When preparing a project inquiry, share the intended application, preliminary equipment schedule, available building drawings, target market, and any unresolved technical requirements so the relevant configuration and interface questions can be reviewed early.